How to use Gantt view in Asana
Add a Gantt tab to an Asana project, create a task, set its start and due dates, and switch to a weekly timeline to see its scheduled bar.

Quick answer
Open a project, click Add tab, and choose Gantt. Add a task, enter a name, then set its start and due dates in the task’s date picker. Choose Weeks from the Gantt scale menu to see a task bar across its scheduled range, and use the date row to confirm the dates.
Steps at a glance
- Open a project and add a Gantt tab.
- Add a task to the Gantt view.
- Enter a clear task name.
- Set the task start date.
- Set the task due date.
- Choose Weeks from the scale menu.
- Confirm the date range and scheduled bar.
Interactive demo
Summary
Gantt view places project tasks on a date-based chart so you can see when work is scheduled. Add a task and set its dates to display a bar, then choose a time scale that makes the schedule easy to read.
Step-by-step guide
Step 1
Add a Gantt tab
Open the project where you want to plan work, then click Add tab. Choose Gantt from the tab picker to open the date-based project view.
Step 2
Add a task to the Gantt
Click Add task in the Gantt view to create a task row. Add the work you want to schedule in this project.
Step 3
Name the Gantt task
Enter a descriptive name in Task name. In this example, the task is named Synthetic Gantt Demo: Prepare launch brief.
Step 4
Set the task start date
On the task row, click Details to open its details pane. Click the existing date range (shown as Today – 13 Nov here) to open the date picker, then enter the task start date in Start date. In this example, the task starts on 16 November 2026.
Step 5
Set the task due date
Enter the end date in Due date. This example ends on 18 November 2026, so the Gantt row shows a 16–18 November range.
Step 6
View the schedule by week
Open the Gantt time-scale menu and choose Weeks. The chart changes to weekly columns while keeping the task’s scheduled range visible.
Step 7
Review the task date range
Check the task’s date row and the bar in the chart. In this example, the row shows 16 – 18 Nov, and the bar spans those dates.
Why this matters
When you are planning a launch, you need to see whether preparation work fits the dates you have in mind. A Gantt bar gives you a visual schedule for the task, while its date range lets you check the start and due dates in the same project view.
Frequently asked questions
How can I see the task’s scheduled dates in Gantt view?
The task row shows its date range, and a bar spans the matching dates on the chart.
Can I change the Gantt time scale?
Yes. The scale menu in this capture offers Days, Weeks, Months, Quarters, Half-year, and Years.
Related guides
Continue with more step-by-step guides for getting work done.
How to add a task in AsanaLearn how to add a task in Asana from a project's List view: click Add task, type a task name, then use the details pane to set an assignee and due date.
How to add a due date in AsanaAdd a due date to an Asana task from List view: click the Due date cell, pick a day in the calendar, and confirm the date shows on the task row.
How to add a collaborator to a task in AsanaAdd a collaborator to an Asana task: open the task details, use the collaborators button, and enter a teammate's email address in the Members field.
How to use goals in AsanaLearn how to find goals in Asana, browse team goals, create a new goal with a title, and start a status update to share how the goal is progressing.
How to use the inbox in AsanaLearn how to open your Asana Inbox, filter notifications, bookmark or archive them, and find them again later from the Bookmarks and Archive tabs.
How to use My Tasks in AsanaLearn how to open My tasks in Asana, work through your sections, add tasks, sort your list, and switch to Calendar view to plan your week.
Create interactive demos like this one — free, no coding required.
Start for free →